Switching chemical input suppliers 100% at once is the #3 most common mistake in electroplating shops. This article presents the protocol Boreto & Cardoso® developed over 53 years of experience to ensure safe transitions.

Why the Protocol Is Necessary

Chemicals from different suppliers have unique characteristics. Even products with the same nominal specification can behave differently because of:

  • Traces of specific impurities
  • Different manufacturing processes
  • The stabilizers used
  • Storage time

Replacing a supplier completely and immediately is like renovating your entire house while you are living in it. It creates instability, rework and losses.

The Common Fatal Mistake

Typical Situation

  1. An electroplating shop finds a supplier with a "better price"
  2. It decides to switch 100% of its inputs immediately
  3. Week 1: Everything is bought from the new supplier
  4. Week 2: Instabilities start to appear
  5. Week 3: Rework becomes constant
  6. Week 4: Losses have wiped out any "savings"

Consequences

Process instability: Parameters that worked perfectly start to fail.

Constant rework: Parts have to be reprocessed, killing productivity.

No way back: With the previous supplier no longer available, correction becomes difficult.

Loss of traceability: No one knows whether the problem lies with the new product or with the process.

The 3-Phase Protocol

Boreto & Cardoso®, serving electroplating shops for 53 years since 1972, developed a protocol that ensures safe transitions.

Phase 1: Document Review

Duration: 1-2 weeks Goal: Confirm the supplier's technical capability

What to Request

Certificates for 3 recent batches:

  • They must be batch-specific (not generic)
  • Analyses of different batches should vary
  • Identical certificates point to fake traceability

Up-to-date SDS:

  • In accordance with ABNT NBR 14725:2019 (the Brazilian standard for chemical hazard communication)
  • All 16 sections complete
  • Valid revision date (maximum of 5 years)
  • Technical lead identified

Company certifications:

  • ISO 9001 or equivalent
  • Environmental licenses
  • Registration with the relevant authorities

Business references:

  • Contacts of customers in the sector
  • Length of relationship
  • Feedback on quality

Information on technical structure:

  • How quality control is performed
  • Equipment available
  • Qualified technical team

Approval Criteria

  • Complete, organized documentation
  • SDS up to date with the standard
  • Batch-to-batch variation <3% (indicates real control)
  • Verifiable positive references

If it fails: Drop the supplier and look for an alternative. It is not worth the risk.

Phase 2: Pilot Test

Duration: 4 weeks minimum Goal: Confirm real performance in the process

Detailed Protocol

1. Buy a small volume

  • Only what is needed for 4 weeks of testing
  • Keep the current supplier delivering as usual

2. Basic pre-use analysis

  • Visual appearance
  • Density (if possible)
  • pH (for alkalis)
  • Confirms the basic specification

3. Use it in parallel with the current product

  • Alternate days: day 1 current, day 2 new, day 3 current...
  • Or separate lines if available
  • NEVER mix the products

4. Document rigorously

  • Process parameters
  • Part quality
  • Processing time
  • Any anomaly observed
  • Feedback from the technical team

5. Evaluate after 4 weeks

  • Equal or better performance
  • No critical problems
  • Team comfortable with the change
  • Adequate cost-benefit

Approval Criteria

Technical performance:

  • Equal or better quality
  • Process stability maintained
  • Adequate reproducibility

Operational aspects:

  • The team approves the product
  • No significant difficulties
  • Logistics worked properly

Cost-benefit:

  • Real savings (not just on price)
  • Taking the whole chain into account

If it fails: Thank the supplier and keep the current one. A test that does not pass has done its job of protecting you; it is no failure.

Phase 3: Gradual Transition

Duration: 6 months Goal: Safe replacement while keeping a backup

Transition Strategy

Months 1-2: 30% new, 70% current

  • Gradually increase use of the new product
  • Monitor quality constantly
  • Keep the current supplier delivering

Months 3-4: 50% new, 50% current

  • The balance allows continuous comparison
  • Detects any deterioration
  • Current supplier still active

Months 5-6: 70% new, 30% current

  • The new supplier becomes the main one
  • The current one becomes the official backup
  • A stable system is in place

What to Monitor

Monthly quality:

  • Scrap rate
  • Rework required
  • Customer complaints

Problem log:

  • Every anomaly documented
  • Root cause analysis
  • Corrective actions implemented

Team feedback:

  • Technicians comfortable
  • Operators adapted
  • Management satisfied

Real cost-benefit:

  • Savings sustained
  • No hidden costs emerging
  • ROI as expected

End Result

After 6 months, you have:

  • A new supplier that is qualified and reliable
  • The previous supplier as an approved backup
  • A documented transition
  • A trained, comfortable team
  • Stable processes

Why Keep a Backup

Single-Source Dependence Is a Risk

A supply problem with a single supplier stops production.

Approved Backup

The previous supplier is already qualified and ready to resume supply if needed.

Alternating Purchases

Keeping the backup active with small periodic purchases maintains the relationship and keeps the product available.

Safety Stock

For critical products, stock covering 30-45 days provides room to maneuver.

The Boreto & Cardoso® Experience

With 53 years serving the Brazilian market since 1972, we developed this protocol based on hundreds of successful transitions.

Our Commitment

Samples for pilot testing: We provide a suitable volume for qualification.

Documentation in advance: Certificates and SDS available before purchase.

Commercial flexibility: Terms suited to the transition phase.

Mistakes to Avoid

Mistake 1: Rushing

Cutting the protocol short to save time leads to bigger problems later.

Mistake 2: Insufficient Testing

4 weeks is the minimum to catch problems that only appear with continuous use.

Mistake 3: Dropping the Previous Supplier

Dropping the current supplier before the transition is complete is an unnecessary risk.

Mistake 4: Not Documenting

Without proper records, it is impossible to identify the causes of problems.

Mistake 5: Ignoring the Team

Technicians and operators notice valuable things that management may miss.

Complete Checklist

Phase 1: Document Review

  • Certificates for 3 recent batches requested
  • SDS up to date with ABNT 14725:2019
  • Company certifications verified
  • Business references checked
  • Technical structure assessed
  • Batch-to-batch variation <3% confirmed
  • Decision: Approve or drop

Phase 2: Pilot Test

  • Small volume purchased (4 weeks)
  • Basic pre-use analysis performed
  • Parallel-use system set up
  • Rigorous documentation in place
  • Full 4 weeks completed
  • Performance evaluated objectively
  • Team consulted and in agreement
  • Decision: Proceed or thank the supplier

Phase 3: Gradual Transition

  • 6-month schedule established
  • Months 1-2: 30/70 completed
  • Months 3-4: 50/50 completed
  • Months 5-6: 70/30 completed
  • Quality monitored monthly
  • Problems documented and resolved
  • Cost-benefit sustained
  • Previous supplier kept as backup

Conclusion

A 3-phase qualification protocol may seem long, but it is the time needed to ensure a safe transition. Haste and short-term savings lead to bigger losses.

Boreto & Cardoso®, with 53 years of experience since 1972, provides documentation in advance, suitable samples and complete certificates of analysis to make the qualification process easier.

Get in Touch

Boreto & Cardoso® Ltda

📞 Head Office: (11) 3931-1722, (11) 2366-6260, WhatsApp (11) 99108-2229, (19) 97685-0233 📞 Limeira Branch: (19) 99458-6331 📱 Branch WhatsApp: (19) 99557-1693 📧 boreto@boreto.com.br

📍 Head Office: R. Alagoas, 30, Santana de Parnaíba/SP, 06530-245 📍 Branch: R. Aratibá, 759, Limeira/SP, 13481-208

🕐 Monday to Friday: 8:00 a.m. to 12:00 p.m. and 1:15 p.m. to 5:30 p.m.


Boreto & Cardoso®: A reliable partner in safe transitions for 53 years.


Note to the reader

This article brings together technical information drawn from various sources, with the aim of broadening knowledge about the raw materials mentioned.

It is informational material only and does not represent any indication of application, formulation or direct recommendation of use on the part of Boreto & Cardoso.

Boreto & Cardoso®, with 53 years of experience, operates strictly in the supply of chemical inputs for a wide range of applications, and it is up to each user to verify the suitability and compliance of their application.